۱Modeling a novel resource–constrained project scheduling problem
اطلاعات انتشار: دومین کنفرانس بین المللی مدیریت و مهندسی صنایع، سال
تعداد صفحات: ۹
This paper provides mathematical analysis for a resource–constrained project scheduling problem in two folds: mathematical formulation, and algorithm development. Correspondingly, the problem has some special assumptions such as (i) resources need a lag time after each use in order to have recovery\service, (ii) each activity can be compressed, and (iii) project available budget is limited. This problem is rarely analyzed in the literature especially for the case of dedicated resources, while we develop a special–purpose algorithm that defeats general–purpose solver Lingo 11.0 on different test problems. The proposed algorithm uses problem characteristics in the form of guiding rules efficiently. At the end, computational experiences are reported.<\div>